Dates

(State: 10.11.2008)

OUTLOOK

November 2008

Test curtain grouting

November - December 2008

Finishing the final design for the final phase of the Bribin hydropower plant

March - April 2009

Shipping of KSB-modules to Indonesia

May - April 2009

Installation of KSB-modules

June 2009

Commissioning and operation of Bribin hydropower plant

MILESTONES

11.10 - 27.10.2008

Installation the controlling system (electro techniques) from Walcher Ltd.

06.10 - 11.10.2008

2nd test Storage and pump water to Kaligoro reservoir

08.10 - 09.10.2008

Kick-Off Meeting of BMBF-Joint Project Integrater Water- and Ressources Management (IWRM) in Gunung Kidul, Yogyakarta in Indonesia

from Sept. 2008

Production of the KSB-modules for the final phase

01.08.2008

Test-run of KSB-Module

29.07. - 01.08.2008

Successfull test storage (see also KIT Pressrelease) as well as  monitoring of barrage movement and seepage water

25.07.2008

Completion of contact grouting at the Barrage

06.07. - 14.07.2008

Installation of VAG-valves at the  flood relief lines

05.05. - 09.05.2008

Presentation of the Project at the IFAT-Convention in Munich

13.03.2008

Presentationon of the project at the 5th symposium "Baustoffe und Bauwerkshaltung" at the University of Karlsruhe (TH)

23.01. - 31.01.2008

Installation the first KSB turbine-pump module

22.01.2008

Completion the barrage

26.12.2007

Interuption of the construction works due to the flood event (Q > 9 m3/s)

25.12.2007

Completion the fifth step concreting work of the barrage (5 of 6)

19.12.2007

Completion the fourth step concreting work of the barrage (4 of 6)

09.12. - 18.12.2007

Installation of the wall pipes at the barrage

05.12.2007

Completion the third step concreting work of the barrage (3 of 6)

02.12.2007

Completion the second step concreting work of the barrage (2 of 6)

27.11.2007

Conpletion the first step concreting work of the barrage (1 of 6)

20.11.2007

Erection the Tower Crane

October 2007

IWRM survey campaign of Bribin water distribution networks and determine the location of drilling test for Gua Seropan, conducted by GIK

August 2007

Continuation of the construction works in Bribin

25.07. - 26.07.07

4th Workshop of Integrated Water Resources Management in Yogyakarta: "Bribin Project after Earthquake 2006 & Opening Ceremony of IWRM",  attended by deputy director Asia, International Office of BMBF, Frau Dr. Heike Bauer and Herr Dr. Andreas Suthhof

07.06. - 11.06.07

Assess the construction site / rock abutment / barrage foundation / rock bolts

04.06. - 06.06.07

Completion of the dewatering works at the construction site

14.04. - 24.04.07

Second blasting activities at the rockfall behind siphon by Indonesian explosive company with support of german professional divers

05.03. - 09.03.07

DAAD-Workshop at the Institute of Technology Bandung (ITB) under coordination of IWG in cooperation with CEDIM

26.01. - 02.02.07

Coordination for the continuation work of the projects (Bribin, Ad-hoc and IWRM)

27.12. - 13.01.07

Evaluation of Ad-hoc project and distribution of  the donation (school books) from the industry partner Herrenknecht to the elementary schools in Gunung Kidul (Ad-hoc)

09.11.2006

3rd Workshop of Integrated Water Resources Management. Subtopic: Prospect for development of Bribin and Seropan caves after earthquake. Organize by Goverment of Yogyakarta Special Province

04.11. - 13.11.2006

First blasting activities at the rockfall behind siphon by Indonesian explosive company with support of german professional divers

07.11. - 08.11.2006

Visit of the German Ambassador for Indonesia, Mr. Freiherr v. Mahltzahn, and BMBF delegation: Mr. RD Ollig, Mr. Lahr and Mrs. Heyn in the project area with project presentation, construction site inspection and cave expedition, as well as meeting with Sri Sultan HB X in Yogyakarta

02.11. - 29.11.2006

Development of sanitation system and toilet building at the Glompong elementary school (Ad-hoc)

27.09. - 29.09.2006

Presentation at Wasserbausymposium Graz 2006 (Water Resources Symposium)

22.09. - 07.10.06

Assignment of german divers for the preparation of blasting works at the rockfall in Gua Bribin; first blasting test at the quarry in Jember, East Java

13.09. - 15.10.06

IWRM - survey campaign in Gua Seropan and the project area by GIK, VA SHS and IWG

24.08. - 07.09.06

Development of drinking water filtration at the Glompong elementary school and installation of UV-Water Filtration at Wonosari hospital (Ad-hoc)

Oct. - Dec. 06

Building three information centre (POSYANIS) in the earthquake area under the frame of a student project "Student Support for Yogya Earthquake Reconstruction Processes" in cooperation with the Civil Engineering Department, University of Gadjah Mada, Yogyakarta (Ad-hoc)

31.07. - 02.08.06

Visit of Deputy Director Asia, International Office of BMBF, Frau Dr. Heike Bauer, in the project area with project presentation and construction site inspection

08.07. - 05.08.06

Assign a German cave diver to Gua Bribin and Seropan for detail investigations of possible damages that were caused by the Earthquake. Find the rockfall behind the last siphon which were released by the earthquake event.

Jun.06 - Aug.06

Reconstruction of school building in Glompong village by Committee Cap-Anamur in cooperation with University of Karlsruhe (Ad-hoc)

Jun.06

Initiate an Ad-hoc project as an additional (aid) project for the Earthquake at Yogyakarta Province, in cooperation with BMBF and Committee Cap-Anamur

30.05.06

First relief action in the catastrophe (earthquake) region by the committee Cap Anamur in cooperation with the university Karlsruhe

27.05.06

Severe earthquake at the province Yogyakarta, with death toll more than 6.000 people. The karst region Gunung Kidul is also highly affected; immediate the waterlevel rises approx. 1,5 m at the Gua Bribin construction site

03.04. - 07.04.06

Presentation of the project at the "Wasser Berlin 2006" with a exhibition model of the IWG

Jan. 2006

Delivery of pump and turbine modules to Indonesia for the implementation of the first phase

Dec. 2005

Completion of platform construction in Gua Bribin

Interuption of the construction works due to the severe flood event (Beginning of the rainy season)

27.11. - 29.11.2005

DAAD-Alumni-Seminar "Engineering for Environment" in Bandung / strategy discussion  with the government authorities regarding the current Bribin Project and the planned IWRM project under the consideration of Sri Sultan HBX

10.11.2005

Press conference at the University of Karlsruhe

Oct. 2005

Delivery of KSB-pump modules as well as the control system from Walcher Ltd.

14.10. - 23.10.2005

Geological and geotechnical evaluation of the subsoil by an expert team from the University of Karlsruhe

27.09. - 28.09.2005

Final inspection of pump modules (I, II) as well as the control system in the test facilities of KSB

Sep. 2005

Completion of dewatering for further construction works in Bribin cave

23.07. - 10.08.2005

Assign a German cave diver team to  investigate the undercurrent of siphon in the construction area. 

Exploration of unknown lateral courses in Gua Bribin for the discharge capacity analysis in the case of flood

25.04. – 29.04.2005

Presentation of the project at the IFAT-Convention in Munich

22.04.2005

4th project workshop with participation of all co-operation partners at "Waldhotel Zollernblick" near Freudenstadt

17.03. + 18.03.2005

Visit of Federal Minister of Education and Research, Edelgard Bulmahn, in the project area with project presentation, building site and cave inspection as well as an audience with Sultan Hamengku Buwono X in Yogyakarta

01.03. + 02.03.2005

Workshop in Yogyakarta within the scope of the IWRM pilot study

24.02.2005

Handing over of final pre-design with the analogue plan to WIKA, DPW and UGM with detailed discussion over the approach plan

31.01.2005

Student excursion to Gua Bribin and to the borehole location in the scope of postgraduate program of UGM

09.12.2004

Company Herrenknecht AG accomplishes break-through with shaft drilling
(ø 2,5 m) in 98,4 m depth

09.12.2004

Coordination meeting concerning the preliminary draft of IWG/IfMB and for further project planning with BATAN, DPW and WIKA in Jakarta

08.12.2004

Coordination meeting concerning the preliminary draft of IWG/IfMB and for further project planning with BAtAN, DPW and WIKA in Yogyakarta

06.12.2004

The acting President Susilo Bambang Yudhoyono visits the building site Bribin

21.10.2004

Project workshop at the IfG of University of Gießen with participation of all Sub project as well as the project agency, the Research Center Karlsruhe

26.08.2004

The Landesschau BW broadcasts a film documentation about the joint project

06.08.2004

Coordination meeting concerning the preliminary draft of IWG/IfMB with BATAN, DPW and WIKA in Jakarta

03.08.2004

Coordination meeting concerning the preliminary draft of IWG/IfMB with BATAN, DPW, WIKA and DIY in Yogyakarta

02.08.2004

Inauguration of building site with attendance of Indonesisan Minister Research and Technology Mr. Hatta Radjasa and Sultan Hamengku Buwono X

07/2004

Beginning of shaft drilling with the vertical drilling machine of the company Herrenknecht AG

25.06. – 26.06.2004

Karstwassersymposium Blaubeuren with a lecture of IWG/IMG about the joint project

18.06. – 20.06.2004

Presentation of the joint project with an information booth at the anniversary celebration of the city of Karlsruhe

03.06.2004

A governmental and parliamentary delegation of Yogyakarta Special Province visits the University of Karlsruhe and the company Herrenknecht AG in Schwanau

17.05.2004

Break through in 98,50 m depth with the second exploratory drilling into Bribin cave

22.04.2004

Project workshop at the IWG with cooperation of all Sub projects as well as with representatives of the project agency

21.04.2004

Completion of the internet presence of the joint project

15.04.2004

Visit of the Indonesian ambassador Mr. Jamtomo at company Herrenknecht AG in Schwanau

29.03.2004

Second exploratory drilling in the range of the planned hydro-power plant

15.03. + 16.03.2004

Project workshop at BATAN in Yogyakarta with participation of Indonesian and German project and co-operation partner

07.02. – 13.02.2004

A delegation of the BMBF / IB (amongst others Mr. Dr. Diehl) accompanied by Prof. Nestmann travels to Indonesia

03.12. – 05.12.2003

Sultan Hamengku Buwono X visits the BMBF in Bonn, the University of Karlsruhe (Meeting with Minister for Environment B.-W. Ulrich Müller and Mayor Manfred Groh) and the company Herrenknecht AG in Schwanau

01.12. – 05.12.2003

Seminar „Water Resources Management in Karst Area“ at Sebelas Maret University, Surakarta

25.11.2003

Project workshop with participation of all Sub projects as well as with representatives of IB (BMBF) and the project agency, the Research Center Karlsruhe

16.08. – 13.09.2003

Measurement campaign in Gua Bribin and the project area by GIK

29.07.2003

Audience with Sultan Hamengku Buwono X in Yogyakarta. Representatives of all Sub projects and the project agency present/introduce the joint project

03.04.2003

Project workshop with participation of all Sub projects AT THE IWG

25.01.2003

Break through in 103 m depth with the first exploratory drilling into Bribin cave
(Start of drilling: End of November)

PRELIMINARY TASKS

06.12.2002

Grant of joint project by BMBF

03/2002

Completion of the feasibility study

09/2000 – 03/2002

4 field investigations in the project area of Gunung Sewu within the scope of IWG's feasibility study

05/2000

IWG applies for a feasibility study about the joint project at the BMBF